Analysis of Project Performance and Completion Time Using Evm and Cpm-Pert Methods (Case Study of Road Reconstruction Project)

Authors

  • Dwi Agus Winarto Civil Engineering, University of Jember, Indonesia
  • Anik Ratnaningsih Civil Engineering, University of Jember, Indonesia
  • Jojok Widodo Soetjipto Civil Engineering, University of Jember, Indonesia

Keywords:

Crithical part method, earn value method, program evaluation report technic

Abstract

The implementation of physical work requires good project control because various conditions can affect the construction implementation process. The calculation of performance analysis is carried out with Earned Value Management (EVM) and the determination of project completion time is carried out by the CPM-PERT method. In this research, it was found that in the 26th week, the schedule performance index value was 0.75758 with an estimated project completion time using the EVM method of 242 days. The critical path shown by the CPM method is M - G - H - N - F - D - E - P - O - K - B – A with a total project completion time of 274 days. Based on the PERT method, the probability of completion time for the project is 71.90%. Acceleration is carried out using the CPM critical path with an optimistic duration of PERT. This acceleration can be done by optimizing the project completion time to 256 days.

References

H. Fahad and E. Endrayadi, "Development of Tourism Sector in Banyuwangi Regency in 2002-2013," Publika Budaya, vol. 5, no. 1, pp. 28–35, 2017.

S. Rizky Widyo Kisworo, Fajar Sri Handayani, "Analysis of Project Acceleration Using Time Cost Trade Off Method with the Addition of Overtime Working Hours and Number of Tools," e-Journal of MATRIX Tek. CIVIL, vol., no. September 2017, pp. 766–776, 2017, [Online]. Available: https://jurnal.uns.ac.id/matriks/article/view/36702

G. Agus Yudha Prawira Adistana, P. Mahardi, M. Firmansyah Sofianto, and D. Eksana Wibowo, "Accuracy of Prediction

Downloads

Published

2023-10-07

How to Cite

Dwi Agus Winarto, Ratnaningsih, A., & Jojok Widodo Soetjipto. (2023). Analysis of Project Performance and Completion Time Using Evm and Cpm-Pert Methods (Case Study of Road Reconstruction Project). International Journal of Sciences: Basic and Applied Research (IJSBAR), 70(1), 269–280. Retrieved from https://gssrr.org/index.php/JournalOfBasicAndApplied/article/view/16224

Issue

Section

Articles